PROJECT

Jean Ross Village

Generator & Switchboard Upgrade

CLIENT

Anglicare

SERVICE

Generator, Switchboards

LOCATION

South Nowra NSW 2541

TIMELINE
4 weeks

PROJECT INFORMATION

This project included the installation of a permanent 250KVA diesel generator, along with a new main switchboard with an in-built automatic transfer switch.

The works involved underground excavations, the installation of new cabling and the restoration of all surfaces affected whilst working on site. Platinum worked closely with an electrical engineer to design and install the new main switchboard which included ATS and surge protection.

jean-ross-side

OBJECTIVES & PRIORITIES

objectives-_fit for purpose
Fit for Purpose
(compliant)
maintenance-cost-savings-icon
Cost
Savings
objectives-_quality workmanship
Quality
Workmanship
fast-response-times-icon
Fast Response
Deadlines

Our team were responsible for the coordination and management to prepare and set up the construction site, which involved engaging with several local contractors for civil works including:

  • Concrete cutting
  • Excavations
  • Concreting
  • Removal of soil

KEY ACHIEVEMENTS

Our team were able to complete this project with a total outage time of only 1.5 hours to the centre. This was a major achievement considering some of the centre's residents require full time care.