Mechanical Services Maximum Capacity Upgrade
CLIENT
Calvary
SERVICE
Mechanical Upgrade
LOCATION
Adelaide
TIMELINE
April 2020
PROJECT INFORMATION
Platinum were engaged to upgrade the mechanical services maximum capacity at Calvary Trevu and Calvary Homestead aged care sites. The works consisted of increasing the supply at both sites to accommodate the removal of evaporative air conditioning and installation of new ducted reverse cycle.
What was involved:
- New consumers mains were installed from the onsite transformer to a new main switchboard at both sites
- The new 600A switchboards were equipped with CT metering and custom built for the design.
- Submains were installed to additional mechanical services switchboards around the facility’s including a 90 Meter cable installed under the carpark.
- End to end project management
- Project safety and development of WHSMP
- Close consideration of the environment that we’re working in to not disrupt staff and residents on-site.
OBJECTIVES & PRIORITIES
Fit for Purpose
(compliant)
(compliant)
Quality
Workmanship
Workmanship
Minimal
Disruption
Disruption
Sustainable
Solutions
Solutions
PROJECT ACHIEVEMENTS
The works were completed and the new mechanical services control was commissioned within the timeline of the project.
RECENT PROJECTS
TOUCH
TESLA MOTORS AUSTRALIA EV Supercharging Station Installation
TOUCH
AMAZON Mezzanine Power and Lighting Fit Out
TOUCH
ST DAVID'S RETIREMENT VILLAGE Generator & Switchboard Upgrade