PROJECT
Schaefer Melbourne
Mezzanine Lighting Installation
CLIENT
SSI Schaefer Systems International
SERVICE
Lighting Installation
LOCATION
Melbourne, VIC
TIMELINE
4 weeks
PROJECT INFORMATION
SSI SCHAEFER SYSTEMS INTERNATIONAL (Schaefer) partnered with Platinum to execute a comprehensive Mezzanine Lighting Installation project at Daimler Melbourne. The project, completed within a tight 4-week timeline in December 2023, focused on enhancing energy efficiency and safety across multiple levels through the deployment of state-of-the-art LED lighting solutions.
OBJECTIVES & PRIORITIES
Fit for Purpose
(compliant)
(compliant)
Quality
Workmanship
Workmanship
Fast Response
Deadlines
Deadlines
Sustainable
Solutions
Solutions
SCOPE OF WORKS
On-site Risk Assessment:
- Conducted a meticulous on-site risk assessment to identify and mitigate potential hazards
Mezzanine Ground Floor:
- Supplied and installed 293 x 36W LED battens with sensors
- Installed 68 x 36W emergency LED battens with sensors
- Deployed 20 x LED Exit signs
Mezzanine Level 1:
- Supplied and installed 293 x 36W LED battens with sensors
- Installed 68 x 36W emergency LED battens with sensors
- Deployed 20 x LED Exit signs
Electrical Infrastructure:
- Supplied and installed a 36-pole distribution board for Mezzanine lighting
- Installed a 100A submain (up to 60m) to the new mezzanine lighting distribution board
Testing and Commissioning:
- Rigorous testing and commissioning procedures were implemented to ensure the functionality and reliability of the entire installation
Documentation:
- Provided comprehensive as-installed documentation upon project completion
KEY ACHIEVEMENTS
- Successful execution of a complex lighting installation project within a condensed 4-week timeline
- Implementation of energy-efficient LED battens with sensors, enhancing overall sustainability
- Improved safety measures through the installation of emergency lighting and LED Exit signs
- Seamless integration of electrical infrastructure, including a distribution board and submain
- Adherence to normal working hours (7:30 am - 4 pm, Mon - Fri) for all project activities