PROJECT

St Leonards Park

External Pole Lighting Upgrade

CLIENT

North Sydney Council

SERVICE

Lighting Upgrade

LOCATION

North Sydney NSW 2060

TIMELINE
12 weeks

PROJECT INFORMATION

Platinum Electricians were awarded the contract to upgrade all external lighting poles throughout St Leonards Park, including the installation of new pits and underground cabling, trenching, under boring, and non-destructive digging. 
 
The team worked in closely with the council representatives, project managers and arborists to deliver a complex project within the grounds of an operating park, working around public events and pedestrians.

PROJECT VALUE: $948,000

stleonardspark7

OBJECTIVES & PRIORITIES

objectives-_fit for purpose
Fit for Purpose
(compliant)
objectives-_quality workmanship
Quality
Workmanship
minimal-disruption-icon
Minimal
Disruptions
energy-icon
Sustainable
Solutions

SCOPE OF WORKS

  • Dilapidation Report completed of the entire park
  • Development of WHSMP
  • Development of Environmental Plan
  • Underground cabling replacement
  • Installation of underground conduits
  • Decommissioning and demolition of existing lighting poles
  • Coordination with lighting engineers to create an efficient design and increase lux in external areas
  • Electrical pit installations
  • Coordination with arborists for protection of existing heritage trees and tree roots throughout the park
  • Installation of power poles to supply temporary power for events
  • Installation of 40 x 6m poles and led fixtures to match the existing heritage poles
  • Reinstatement of all services
stleonardspark15
stleonardspark6
stleonardspark9
stleonardspark10
stleonardspark13
stleonardspark11
stleonardspark12
stleonardspark14
stleonardspark8

KEY ACHIEVEMENTS

  • Minimal disruption to the operations of the park
  • Temporary fencing setup around all work areas
  • Traffic and pedestrian management plan completed to divert all pedestrians around work areas
  • Close communication and coordination with all key stakeholders
     